Moving Forward » Moving Forward

Moving Forward

 
BOND CONSTRUCTION UPDATE
*This information will change as progress is made, please check back often.
 
Project
Estimated
Project Cost
 
Start Date
Project
Status
NISD Workforce Building
(Formerly the W.B. Bizzell Academy Building)
 
$70,814 May 2018 Complete
John C. Webb Elementary
 
 
$755,820 May 2018 Complete
Navasota Education Learning Center - NELC
(Formerly OLD Webb Elementary)
 
$3,894,798 - $4,248,871 May 2018 Complete
Navasota Junior High
 
   April, 2020  Complete
Navasota High School 
 
   April, 2020  Complete
 Brosig Auditorium
  June, 2020   
Rock Gym 
  June, 2020   
 Ag Farm
  June, 2020   
 
     
 
     
 
     
  
 
BEGINNING OF BOND PLANNING
 
First planning meeting was held on November 29 to discuss priorities
for bond construction and remodeling projects of NISD campuses
Live Oak Public Finance,
NISD School Board Facility Committee, and NISD Administration.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Design and Planning Meeting June, 2018
NISD Administrators,  Principals, Assistant Principals, Fine Arts Staff, and CTE Staff met in June, to discuss the design and planning of new spaces and additions to the High School and Junior High.